A MAJOR CARIBBEAN MARINE CONSTRUCTION COMPANY
As Featured….
SOCIAL MEDIA UPDATES
BVI CRUISE PIER EXPANSION
Meridian was contracted by the Government of the Virgin Islands through the BVI Ports Authority to undertake the marine construction and dredging for the Cruise Pier Expansion project.
MARINE CONSTRUCTION
Using our engineered precast concrete dock systems in the construction of docks, marinas and bulkheads, we manufacture our own templates, precast piles, caps and slabs for a precision fit for any marine structure

Catsy – A Dry Salvage Operation
Meridian Construction Ltd was engaged to undertake the dry salvage of the 30-tonne Sunreef 62, Catsy, which had been flipped upside down during the passage of Hurricane Irma on September 6, 2017.
This complicated project, where the priority was to minimize further damage, needed three cranes, and an excavator. A team comprised of Meridian, Commercial Dive Services, and B&G Lifting, undertook the 10-hour project with six hours of prep work and four hours of lifting, moving, and flipping this yacht.

Meridian teams up with Commercial Dive Services in marine salvage work following Cat 5 hurricanes
Meridian Construction Ltd teamed up with Commercial Dive Services in response to the restoration efforts of the marinas and marine industry in the British Virgin Islands following the passage of Hurricanes Irma and Maria. Using Meridian’s inventory of cranes and barges, salvage and recovery work has been carried out by the team on locations in […]

Meridian Plays Key Role In Installation Of Sewage Infrastructure – Part Two
Installation of Sewage Treatment Pump Station. Meridian was contracted by Biwater International to construct the pump station and install the pumps. This work was technically difficult as the pump station, located at a depth of 25’, is situated on reclaimed land and below the water table. Additionally the subsurface is running, waterlogged sand. This meant that no ordinary excavation could be conducted and required Meridian to devise a method to construct and install these 15-ft diameter, reinforced concrete tanks.
MOBILIZATION & DEMOBILIZATION
A major upfront expense of any project. Meridian carefully manages its mobilization and demobilization plans. We source the skilled workforce and ensure that all requisite plant, equipment and materials are on site at the start of the project and removed on completion.
HERITAGE QUAY CRUISE PIER ANTIGUA
Meridian Construction Ltd was the Caribbean marine contractor engaged by the St. John’s Development Corporation Heritage Quay, Antigua